Screen operational measures first
Inspect idle running, compressed-air leaks, setpoints, maintenance and scheduling before assuming equipment replacement is the best option. Ask a competent technician to verify the measure, its effect on safety and quality, and the conditions under which the estimate holds.
Compare equivalent service
For competing motors, pumps or compressors, compare performance at the actual operating load and hours, not only nameplate power. Include installation, downtime, maintenance, useful life, spare parts and measurement costs. Keep mandatory replacements and incremental efficiency expenditure identifiable.
Worked example — fictional upgrade
An upgrade costs VND 180 million. Estimated electricity savings are 24,000 kWh/year at an assumed avoidable cost of VND 2,000/kWh, or VND 48 million/year. Additional maintenance costs VND 8 million/year. Net benefit is VND 40 million/year and simple payback is 4.5 years. At only 70% of expected savings, net benefit becomes VND 25.6 million and payback about 7.0 years. Neither price is an official tariff or lender quote.
Practice
Compare two quotations in one sheet: service delivered, baseline, predicted savings, investment, operating costs, downtime, warranty, evidence quality and monitoring method. Record who will verify each assumption. For a full investment decision, model cash-flow timing, financing costs, taxes and residual value as applicable; simple payback omits these.
Knowledge check
Why should the procurement team ask for savings at the real load? Answer: rated efficiency and actual duty cycles can differ; the financial estimate must reflect the operating conditions.