LESSON 01

Define the project before classifying it

Separate the investment, its environmental outcome and the wider business.

Start with the investment, not the label

A company can operate both ordinary and environmentally beneficial activities. The object of review is the defined investment: its assets, site, expenditures, commissioning date and operating boundary. Do not classify the whole company merely because it proposes one improvement.

Write a measurable objective

Describe the existing condition, the proposed change and the expected outcome in physical units. For a water-reuse system, record freshwater intake, wastewater volume and quality, and the process receiving treated water. A cost saving is useful to finance staff, but it does not by itself establish an environmental outcome.

Worked example

A fictional packaging SME plans a VND 900 million production-line upgrade: VND 600 million for efficient drives, VND 200 million for unrelated office refurbishment and VND 100 million for installation. Identify which expenditures support the environmental project and document the allocation of installation costs. Do not automatically classify all VND 900 million as green.

Practice

Write a one-page scope with site, equipment, baseline, expected outcome, budget, excluded expenditure and responsible person. Mark uncertain cost allocations as pending rather than guessing. Attach the available quotation or process diagram.

Check your understanding

Does buying efficient equipment make all business expenditure green? No. The project boundary and relevant eligibility criteria must be evaluated separately. Your scope is a starting point for review, not a certificate.

Educational material for preliminary preparation, not legal advice, a formal green classification, certification or a lending decision. Confirm the current applicable rules and the lender’s requirements. All numerical examples are fictional.