Find the closest candidate activity
Search the applicable official appendix for the actual activity, not just an attractive sector name. Copy the exact locator, record the unit, boundary, reference period and required calculation. A similar project category may have different conditions. Where a standard is referenced, note its exact edition and check access rights.
Use an evidence matrix
For each applicable criterion, record a reference, applicability, expected proof, existing evidence, owner and status. Use four preliminary statuses: supported by available evidence, gap identified, not applicable with reason, or needs verification. A blank answer is not a pass or failure.
Worked example
A fictional factory consumes 120,000 kWh to produce 30,000 units in its baseline period, or 4 kWh per unit. After a change, it consumes 108,000 kWh for 32,000 units, or 3.375 kWh per unit. Its energy intensity falls by about 15.6%, whereas absolute consumption falls by 10%. These are different metrics; neither percentage is a legal threshold. Use the metric required by the actual criterion and document any boundary changes.
Practice
Build three rows for your project: one technical criterion, one environmental obligation and one measurement requirement. Record the actual clause or mark it pending, identify proof, and explain what is still missing. Include a date and named responsible role.
Check your understanding
Can a vendor’s estimate alone establish achieved savings? No. It is forecast evidence. Actual results require suitable operational measurements and comparable conditions.
Educational material for preliminary preparation, not legal advice, a formal green classification, certification or a lending decision. Confirm the current applicable rules and the lender’s requirements. All numerical examples are fictional.