Use incremental cash flows
Compare the business with and without the investment under comparable operating assumptions. List changes in revenue, energy, materials, maintenance, staffing and working capital. Separate one-off capital spending from recurring expenses. Model the entire business’s cash position when considering repayment; a project saving is only one contributor.
Worked example: energy saving
A fictional upgrade costs VND 600 million and is forecast to save 75,000 kWh each year at an illustrative VND 2,000/kWh. Gross electricity savings equal VND 150 million. Additional annual maintenance is VND 20 million, giving VND 130 million net annual operating savings before tax and financing. Simple payback is about 4.62 years. This is not a discounted valuation or repayment forecast.
Stress-test the proposal
If realized savings are 20% below the forecast, gross savings fall to VND 120 million; after maintenance, net savings are VND 100 million and simple payback is six years. Also test lower production, delay and higher installation costs. Compare actual debt service, taxes and operating cash requirements using the lender’s terms only when available.
Practice
Build base and downside cases with energy quantity, price, utilization, maintenance, capex and start date. Label each assumption with its source, owner and date. Add a monthly cash-flow timeline including other business obligations. Do not substitute profit for cash available to pay debt.
Check your understanding
Does a simple payback shorter than a loan term prove repayment ability? No. The timing of cash flows, financing costs, other liabilities and operating risks can change the result.
Educational material for preliminary preparation, not legal advice, a formal green classification, certification or a lending decision. Confirm the current applicable rules and the lender’s requirements. All numerical examples are fictional.