LESSON 03

Turn environmental benefits into a business case

Build a transparent operating-savings estimate and test the limitations of simple payback.

Connect physical units to money

Start with measured activity, such as electricity use, water consumption or material losses. Estimate the change expected from the investment, then multiply by the applicable avoided unit cost. Account for new maintenance costs and other relevant cash effects. Keep environmental results separate from the financial estimate so both can be reviewed.

Worked example — fictional compressor

Assume the installed investment costs VND 180 million, annual electricity savings are 18,000 kWh, and the avoided variable electricity cost is VND 2,500/kWh. Annual gross savings are VND 45 million. If additional annual maintenance costs VND 5 million, estimated net operating savings are VND 40 million. Simple payback is 180 ÷ 40 = 4.5 years. These are invented training inputs, not market tariffs or bank terms.

Stress-test the assumption

If savings are only 12,000 kWh, gross savings fall to VND 30 million; net savings become VND 25 million and simple payback rises to 7.2 years, assuming other inputs are unchanged. Record why the lower estimate is plausible. Check the effect of downtime, output changes, tariff structure and installation delays.

Do not confuse payback with repayment capacity

Simple payback excludes the timing of financing cash flows, interest, tax effects, discounting and residual value. A lender assesses broader business cash flow and obligations. Map estimated project savings and actual debt payments month by month using the proposed contract terms. If data are unavailable, mark them as missing and request a written financing offer.

Practice and self-check

Create a three-row comparison with conservative, base and optimistic savings. For each row record the input evidence, annual net savings and payback. Question: if project payback is 4.5 years, is a four-year loan affordable? Answer: not enough information; repayment schedules and business cash flows must be evaluated.